I used historical analysis to identify an area of improvement. We noticed one type of our components was vastly more reliable than the other type. Therefore, my team and I planned to convert some of the unreliable components to the more reliable components.
My team and I planned to complete these conversions by installing 3 parts:
• Pack-Off System
• Feedthrough Arm
• RMS Connector
I travelled to site to oversee the first conversion! I arranged with vendors for the necessary supplies and services, and wrote the execution program for the site team.
Here is the team installing the pack-off system:
And the feedthrough arm:
Here is the final picture of the oil wellhead. Notice the large L-shaped feedthrough arm.
For comparison, here is what the well originally looked like: